Project SG-69 Update: Phase II
Oct. 5th, 2005 11:54 pmWe're getting ready to set up the gate this Saturday on the eastern patio of the Doubletree... with some upgrades
- Braces cut and drilled to make the frame rigid enough to be freestanding.
- Frame Spars drilled with second set of holes to bolt into the corner braces
- A second set of ring arcs painted and cut (out of 3/16" black foamcore under the paint) to put on the reverse of the gate, so it will look good from the back, too.